Operations Management : critical path, time & slack

The R&D dept. is planning to bid on a large project for the development of a new communication system for commercial planes.  The accompanying table shows the activities, time & sequence required:
Activity Immediate predecessor Time (weeks)
A --- 3
B A 2
C A 4
D A 4
E B 6
F C,D 6
G D,F 2
H D 3
I E,G,H 3

A.) What is the critical path?
B.) Suppose you want to shorten the completion time as much as possible, & you have the option of shortening any or all of B,C,D, and G each one week.  Which would you shorten?
C.) What is the new critical path & earliest completion time? (from b's answer  I think)
Please solve using Microsoft Excel & show any work if possible.  Thanks!

Attached file(s):
Attachments
The R.docx  View File

Solution Summary

This problem provides calculation of critical path, critical time and slack for problem on operations management.

Solution
What is this?
By OTA - Overall OTA Rating
Neha Jain, ME - 4.9/5
Purchase Cost Now
$2.19 CAD (was ~$3.99)
Included in Download
  • Plain text response
  • Attached file(s):
    • 163468.xls
Why you can trust BrainMass.com
  • Your Information is Secure
  • Best Online Academic Help Service
  • Students find real academic Success
Related Solutions
Browse