Project Management - Critical Path - Given the following data, find the critical path and the minimum project completion time.
Activity; te(expected activity time); Preceding Activity
1-2; 3; -
2-4; 8; 1-2
2-3; 6; 1-2
2-5; 2; 1- ...
Critical Path, duration, and slack of the decision tree project. - In the attached problem I need to draw a decision tree and fill in the table. I also need to find the critical path and duration and slack.
See attached file for full problem description.
Activi ...
Pert network diagram - In the project network shown in the follwoing figure, the number alongside each activity represents known duration in weeks.
Determine the following
earliest and latest start and finsih times
...