Work Breakdown Structure

I have the layout of the chart I am stuck at this point though.  I need help.  Thanks

Develop a Work Breakdown Structure (WBS) and project schedule in a Gantt format for the E-Mail Upgrade Project described in the scenario. The WBS and resultant schedule should contain the following high-level activities:

1.0 Evaluate User & System Requirements
2.0 Evaluate ODHS Network Suitability
3.0 Conduct E-mail System Selection
4.0 Upgrade ODHS Network & Hardware
5.0 Develop E-mail Training
6.0 Deploy E-mail System

Each of the six WBS elements should be decomposed into two or more activities; additionally, three of these six elements should be decomposed into a third level consisting of at least two more activities. Thus, there should be six high level WBS elements, twelve or more second level activities (two per the six elements), and six third level activities. Use the format described above to define the activities (action verb followed by subject, such as Deploy E-mail System).


The Gantt chart should be developed based on the WBS (all activities should be detailed on the Gantt chart). The Gantt chart should reflect the proper dependencies of each of the activities (for example, you can't have "Deploy E-mail System" before "Evaluate User Requirements"). For activity duration, provide a reasonable estimate of the time you expect each activity to take; while students are not expected to provide accurate durations, durations should be reasonably defensible and logical. For formatting ease, high level activities should be left justified while second and third level activities should be indented below their parent activities.

Attached file(s):
Attachments
Unit 2 IP.mpp  View File

Solution Summary

Develop a Work Breakdown Structure (WBS) and project schedule in a Gantt format for the E-Mail Upgrade Project described in the scenario. The WBS and resultant schedule should contain the following high-level activities:

Solution
What is this?
By OTA - Overall OTA Rating
Jai Advani, PhD  - 4.9/5
Purchase Cost Now
$2.19 CAD (was ~$11.97)
Included in Download
  • Plain text response
  • Attached file(s):
    • 161300.xls
Why you can trust BrainMass.com
  • Your Information is Secure
  • Best Online Academic Help Service
  • Students find real academic Success
Related Solutions
  • Project Management - WBS with Example - Develop a Work Breakdown Structure (WBS) and project schedule in a Gantt format for an E-Mail Upgrade Project . The WBS and resultant schedule should contain the following high-level activities: 1. ...
  • Project Management - Project Scheduling - 1) What is the difference between a task flow network diagram and a Gantt chart. What is the relative value of each to the project manager? 2) Gantt charts have a potential disadvantage when it c ...
  • Project Management-gantt chart - Could you replicate what I did where I show the bars within a Gantt Chart as shown on the attached? I created this from a trial sample from the internet, but would like to duplicate this without the ...
  • Operation Management - Gantt Chart - Which of the following is NOT true about the Gantt chart? a - it is more for time planning than for sequencing purposes b - the chart is used in scheduling resources as well as jobs c - the u ...
  • Construct a Gantt chart and project network - Construct a Gantt chart and project network.