b. WORK BREAKDOWN SCHEDULE (WBS)









Work Breakdown Structure for CDGA





Project: Johnson Family 3-car Garage w/living quarters











WBS Code Task/Subtask Duration Milestones Who



1 Remove Trees from site 2 Days

Johnson



2 Draw up blue prints 2 Days

CDGA



3 Measure site 1 Day

CDGA



4 Submit plans city approval 7 Days

CDGA



4.1 Survey site 1 Day

CDGA



4.2 Stake site 1 Day

CDGA



5 Order grader Equip. Sim

CDGA



6 Get on Utilities Calander Sim

CDGA



Site and architectural plans approval Sim X



7 Grade site-remove debris 1.5 Days

?



6.1 Utilities dig 2 trenches 2 Days

City



8 Get on foundation Calander Sim

CDGA



9 Get on Carpenters Calendar Sim

CDGA



10 Order Windows Sim

CDGA



8.1 Order four cement trucks Sim

?



6.2 Utilities connected 2 Days X City



6.3 City back fills trenches .25 days

City



7.1 Site is final regrade .25 Days

?



8.2 Slab is poured 1 Day

?



Slab foundation finished

X ?



8.3 2-days Dry Time 2 Days

?



11 Order framing Materials Sim

CDGA



12 Order Steel Siding Sim

CDGA



10.1 Windows Arrive Sim





8.4 Foundation Inspected Sim

City



11.1 Framing Materials Arrive Sim





9.1 Carpenters arrive Sim





12 Order Sheet Rock/Insul. Sim

CDGA



11.2 Frame base and walls 1 Day

CDGA



11.3 Finish Fr. walls/Start Truss 1 Day

CDGA



11.4 Finish truss/Start wall boards 1 Day

CDGA



13 Plumb/Eletr. rough-in Sim P&E



11.5 Finish walls & windows 1 Day

CDGA



14 Start Siding 4 Days

CDGA



15 Order Counters/Cab./Floor Sim

CDGA



16 Order Appliances Sim

CDGA



17 Roof Shingles started 3 Days

CDGA



13.1 Plumb/Eletr. Rough Insp. Sim

P&E



18 Rock walls/Insul. 5 Days

CDGA



18.1 Tape/Mud 1 Day

CDGA



18.2 Tape/Mud & Sand 1 Day

CDGA



Finish Siding & Shingles Sim X CDGA



18.3 Mud & Sand 1 Day

CDGA



18.4 Mud & Sand 1 Day

CDGA



18.5 Spray ceiling .5 Days

CDGA



18.6 Final Mud & Sand 1 Day

CDGA



15.1 Install Count/Cab./Floor 3 Days

CDGA



19 Paint & Trim 2 Days

Laborer



5.1 Order grader Equip. Sim

?



16.1 Install Appliances Sim

CDGA



19.1 Finish Paint & Trim Sim

Laborer



13.2 Plumb./Eletr. Finish Sim

P&E



7.2 Grade Drive/sidewalk .75 Day

?



13.3 Plumb./Eletr. Finish 2 Days

P&E



Plumb/Ele. Final Inspect. Sim X City



8.5 Order two cement trucks Sim

?



8.6 Pour Drive/Sidewalk 1 Day

?



8.7 2-days Dry Time 2 Days

?



Driveway & sidewalk finished Sim X ?



20 Clean up site .5 Days

Laborer



21 Pass final inspection .25 Days X City/CDGA











Task flow network and critical path

Arrange WBS elements in the form of a task-flow network to determine
task

dependencies. Determine the critical path, including necessary resource
allocation to

achieve project objectives in the appropriate timeframe. Indicate
earliest occurrence

times and highlight the critical path. This can be done by flow charting

software.
Solution
What is this?
By OTA - Overall OTA Rating
Departed OTA
Purchase Cost Now
$2.19 CAD (was ~$59.85)
Included in Download
  • Plain text response
  • Attached file(s):
    • FLOW.doc
Why you can trust BrainMass.com
  • Your Information is Secure
  • Best Online Academic Help Service
  • Students find real academic Success
Related Solutions
Browse