Business Homework Solutions
Problem
#41840

a) Determine the critical path. b) How many weeks will the project take to complete? c) Suppose F could be shortened by two weeks and B by one week. How would this affect the completing date?

6. Here is a CPM network with activity times in weeks:
a) Determine the critical path.
b) How many weeks will the project take to complete?
c) Suppose F could be shortened by two weeks and B by one week. How would this affect the completing date?

Please see attached.

Attached file(s):
Attachments
6-pg91.pdf  View File

Attachment Content Summary (Note: view attachment at the above link before purchasing. Actual attachment content may vary slightly from that shown below.)

6-pg91.pdf
,.
!I.
PROJECT MANAGEMENT chapter 3 91


C. If activities I and 10 cannot be shortened, but activities 2 through 9 can be shortened to a min-
imum of one week each at a cost of $10,000 per week, which activities would you shorten to
cut the project by four weeks?
5 The following represents a project that should be scheduled using CPM:

TIMES(DAYS)

ACTIVITY IMMEDIATE PREDECESSORS a m b

A 1 3 5
B 1 2 3
C A 1 2 3
D A 2 3 4
E B 3 4 11
F C,D 3 4 5
II'
G D, E 1 4 6
H F,G 2 4 5


a. Draw the network.
b. What is the critical path?
c. What is the expected project completion time?
d. What is the probability of completing this project within 16 days?
6 Here is a CPM network with activity times in weeks:




a. Determinethe critical path.
b. How many weeks will the project take to complete?
c. SupposeF could be shortened by two weeks and B by one week. How would this affect the
completion date?
7 The following table represents a plan for a project:

JOB No. PREDECESSORJOB(S) a m b

2 3 4

2 1 1 2 3

3 1 4 5 12

4 1 3 4 11 IIII

5 2 1 3 5
6 3 1 2 3
7 4 1 8 9
8 5,6 2 4 6

9 8 2 4 12
10 7 3 4 5
11 9,10 5 7 8


a. Construct the appropriate network diagram.
b. Indicate the critical path.
c. What is the expected completion time for the project?
d. You can accomplish anyone of the following at an additional cost of $1,500:
(1) Reduce job 5 by two days.
(2) Reduce job 3 by two days.
(3) Reduce job 7 by two days.



I"

Solution Summary

Determines the critical path and time for completion of project.

Solution
What is this?
By OTA - Overall OTA Rating
Purchase Cost Now
$2.19 CAD (was ~$19.95)
Included in Download
  • Plain text response
  • Attached file(s):
    • 41840-business-critical path.xls
$2.19 Instant Download
Add to Cart
Why you can trust BrainMass.com
  • Your Information is Secure
  • Best Online Academic Help Service
  • Students find real academic Success
Related Solutions
  • Operation Management - Slack Time - A manufacturer of electricity and steam cogeneration systems produces low-cost and environmentally sound turbine/generator sets for use at locations were steam is to be consumed. The project network f ...
  • Project Management:(CPM Problem) Calculate EFT,LFT, Slack, Critical path - Use Excel to solve the following: Given the following network with activity times in months, determine the earliest and latest activity times and slack for each activity. Indicate the critical pat ...
  • PDM/CPM Chart - Given the following network: (a) What is the critical path? (b) How long will it take to complete this project? (c) Can activity B be delayed without delaying the completion of the project? If so ...
  • Project tracking using CPM: draw a network. What is the critical path. - I have to track the following activites here at work for a project to be scheduled using CPM. Activity Immediate Predecessor Time (Week) A none 6 B A ...
  • Critical Path - CPM network - A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate predecessor of F. The activity durations are D=4, E=3, F=8. Which is the correct ...
Browse