Microsoft Project 2000 has templates that can be used for getting started in project management. These are good but unfortunately, these templates don't include costs (such as hourly and overtime rates) for resources allocated.
How can I include costs?
The solution explains two ways to set up standard and overtime hourly rates in Microsoft Project. The explanation includes the details of exactly how to accomplish it.