1) Organizers for a political convention have determined ten activities that must be done before the convention begins.
Activity Immediate Predecessors Time (Weeks)
A --- 10
B A 4
C B 2
D B 2
E A 6
F A, C 3
G D 4
H F, G 6
I D 5
J E 4
Please:
a. Draw out the PERT/CPM network for the project.
b. Identify the critical path.
c. Determine how many weeks prior to the convention the work must begin.
Thank you in advance for your insight.
The solution draws the PERT/CPM network for the project, identifies the critical path and determines the duration of the project.