CONTROL CHARTS
Assignment Overview
You have taken data from a production process in order to develop an Xbar control chart. You have 25 samples of data with 5 parts measured in each sample to get the Xbar and R (Range). Use this data shown in the table.
The Case 5 Excel file (same file in Background) contains the data:
Sample 1 2 3 4 5 Xbar R
1 1.55 1.58 1.64 1.67 1.50 1.588 0.17
2 1.52 1.62 1.71 1.74 1.60
3 1.47 1.57 1.44 1.56 1.42
4 1.67 1.73 1.76 1.64 1.64
5 1.46 1.52 1.60 1.41 1.43
6 1.44 1.50 1.53 1.37 1.41
7 1.55 1.64 1.70 1.53 1.58
8 1.54 1.72 1.66 1.52 1.57
9 1.48 1.60 1.57 1.46 1.51
10 1.43 1.55 1.52 1.43 1.46
11 1.40 1.52 1.56 1.38 1.43
12 1.60 1.44 1.55 1.58 1.49
13 1.48 1.46 1.57 1.60 1.65
14 1.56 1.54 1.65 1.68 1.59
15 1.42 1.39 1.51 1.54 1.45
16 1.70 1.71 1.61 1.73 1.64
17 1.51 1.35 1.37 1.49 1.40
18 1.41 1.32 1.44 1.32 1.35
19 1.69 1.58 1.75 1.60 1.63
20 1.67 1.56 1.79 1.58 1.61
21 1.65 1.57 1.68 1.56 1.59
22 1.52 1.46 1.55 1.45 1.46
23 1.51 1.41 1.54 1.42 1.45
24 1.62 1.51 1.69 1.53 1.56
25 1.57 1.46 1.60 1.47 1.51
1. First plot the data using (Excel).
2. Then determine the UCL and LCL. Do any of the data points need to be thrown out? If so, then recalculate the UCL and LCL.
3. Then you begin to plot results on this chart. Here are the next 6 samples of data (sample size = 5).
Sample # 1 2 3 4 5 Xbar
26 1.51 1.35 1.37 1.49 1.40
27 1.41 1.32 1.44 1.32 1.35
28 1.69 1.58 1.72 1.60 1.63
29 1.67 1.56 1.70 1.58 1.61
30 1.65 1.57 1.68 1.56 1.59
31 1.52 1.46 1.55 1.45 1.46
Plot these on the control chart.
4. Is the process in control?
Provide a one page paper discussing the problem, what you did to solve it and what your specific recommendation or plan is for monitoring quality. Upload your paper into the Case 5 area and upload your Excel file into Additional Files.
Assignment Expectations
1. Answer questions with clarity and show the detailed steps for calculation if any. Turn in your answers by module due date.

See attachment for better table representation.

Attachments
Purchase this Solution

Solution Summary

This solution contains 25 samples of 5 observations that each are used to construct an X-bar control chart and then based on the initial X-bar chart a revised X-bar chart is made and 6 new samples are then plotted in the new, revised X-bar control chart to see if the production process is in control or not.

Solution Preview

I have attached an Excel spreadsheet as well as an MS Word doc that together give you everything that ...

Purchase this Solution


Free BrainMass Quizzes
Measures of Central Tendency

This quiz evaluates the students understanding of the measures of central tendency seen in statistics. This quiz is specifically designed to incorporate the measures of central tendency as they relate to psychological research.

Know Your Statistical Concepts

Each question is a choice-summary multiple choice question that presents you with a statistical concept and then 4 numbered statements. You must decide which (if any) of the numbered statements is/are true as they relate to the statistical concept.

Measures of Central Tendency

Tests knowledge of the three main measures of central tendency, including some simple calculation questions.

Terms and Definitions for Statistics

This quiz covers basic terms and definitions of statistics.