Reese Construction Corporation contracted to construct a building for $1,500,000. Construction began in 2007 and was completed in 2008. Data relating to the contract are summarized below:

Year Ended
Dec. 31
2007 2008
Costs incurred $600,000 $450,000
Estimated cost to complete $400,000 -0-

Reese uses the percentage-of-completion method as the basis for income recognition. For the years ended December 31, 2007, and 2008, respectively, Reese should report gross profit of

A. $270,000 and $180,000.

B. $300,000 and $150,000.

C. $900,000 and $600,000.

D. $0 and $450,000.

Purchase this Solution

Solution Summary

The solution using the percentage-of-completion method to report the gross profit.

Solution Preview

Year Ended
Dec. 31
2007 2008
Costs incurred $600,000 ...

Purchase this Solution


Free BrainMass Quizzes
Organizational Behavior (OB)

The organizational behavior (OB) quiz will help you better understand organizational behavior through the lens of managers including workforce diversity.

Marketing Management Philosophies Quiz

A test on how well a student understands the basic assumptions of marketers on buyers that will form a basis of their marketing strategies.

Understanding Management

This quiz will help you understand the dimensions of employee diversity as well as how to manage a culturally diverse workforce.

Lean your Process

This quiz will help you understand the basic concepts of Lean.

Introduction to Finance

This quiz test introductory finance topics.