The Durant Company is installing an absorption standard-cost system and a flexible-overhead budget. Standard costs have recently been developed for its only product and are as follows:

Direct materials 3 pounds @ $20 $60
Direct labor 2 hours @ $14 28
Variable overhead 2 hours @ $5 10
Fixed overhead ?
Standard cost per unit of finished product $ ?

Expected production activity is expressed as 7,500 standard direct-labor hours per month. Fixed overhead is expected to be $60,000 per month. The predetermined fixed-overhead rate for product costing is not changed from month to month.

1. Calculate the proper fixed-overhead rate per standard direct-labor hour and per unit.

2. Assume that 6,000 standard direct-labor hours are allowed for the output achieved during a given month. Actual variable overhead of $31,000 was incurred; actual fixed overhead amounted to $62,000. Calculate the
a. Fixed-overhead flexible-budget variance
b. Fixed-overhead production-volume variance
c. Variable-overhead flexible-budget variance

Purchase this Solution

Solution Summary

The solution explains how to calculate various overhead variances

Purchase this Solution


Free BrainMass Quizzes
Income Streams

In our ever changing world, developing secondary income streams is becoming more important. This quiz provides a brief overview of income sources.

Cost Concepts: Analyzing Costs in Managerial Accounting

This quiz gives students the opportunity to assess their knowledge of cost concepts used in managerial accounting such as opportunity costs, marginal costs, relevant costs and the benefits and relationships that derive from them.

Motivation

This tests some key elements of major motivation theories.

IPOs

This Quiz is compiled of questions that pertain to IPOs (Initial Public Offerings)

Academic Reading and Writing: Critical Thinking

Importance of Critical Thinking