1. Long lead times are the result of:

a. long setup times
b. large batch sizes
c. large inventories
d. all of the above

2. How are the objectives of Just-in-Time (JIT) manufacturing achieved?

a. Product-oriented production layout
b. Employee involvement
c. Supplier partnering
d. All of the above

3. Which of the following drive work in process inventory levels higher?

a. Machine breakdowns
b. Production rate losses
c. Rework processing
d. All of the above

4. Which of the following is characteristic of a just-in-time (JIT) system?

a. Fewer work in process account transactions
b. Work in process and raw materials accounts combine
c. Elimination of the direct labor account
d. All of the above

5. Which of the following is characteristic of a traditional cost system?

a. Many work in process account transactions
b. Reliance on financial performance measures
c. Many process control points
d. All of the above

6. Which of the following is best suited to providing timely and focused performance information?

a. Nonfinancial information
b. Financial accounting information
c. Cost accounting information
d. Variance analysis

7. Foley Electronics Corporation manufactures and assembles electronic motor drives for video cameras. The company assembles the motor drives for several accounts. The process consists of a just-in-time cell for each customer. The following information relates only to one customer's just-in-time cell for the month of August: labor and overhead, $6,400,000; materials costs, $160,000. Planned production included 800 hours to produce 6,400 motor drives. However, actual production was 5.200 units, and motor drives shipped amounted to 5,040 units. From the foregoing information, determine the budgeted cell conversion cost per hour.

a. $8,800
b. $800
c. $7,200
d. $8,000

8. Foley Electronics Corporation manufactures and assembles electronic motor drives for video cameras. The company assembles the motor drives for several accounts. The process consists of a just-in-time cell for each customer. The following information relates only to one customer's just-in-time cell for the month of August: labor and overhead, $6,400,000; materials costs, $160,000. Planned production included 800 hours to produce 6,400 motor drives. However, actual production was 5.200 units, and motor drives shipped amounted to 5,040 units. From the foregoing information, determine the budgeted cell conversion cost per unit.

a. $250.00
b. $267.00
c. $308.00
d. $317.00

9. Foley Electronics Corporation manufactures and assembles electronic motor drives for video cameras. The company assembles the motor drives for several accounts. The process consists of a just-in-time cell for each customer. The following information relates only to one customer's just-in-time cell for the month of August: labor and overhead, $6,400,000; materials costs, $160,000. Planned production included 800 hours to produce 6,400 motor drives. However, actual production was 5.200 units, and motor drives shipped amounted to 5,040 units. From the foregoing information, determine the budgeted materials cost per unit.

a. $25.00
b. $26.67
c. $30.77
d. $31.75

10. Foley Electronics Corporation manufactures and assembles electronic motor drives for video cameras. The company assembles the motor drives for several accounts. The process consists of a just-in-time cell for each customer. The following information relates only to one customer's just-in-time cell for the month of August: labor and overhead, $6,400,000; materials costs, $160,000. Planned production included 800 hours to produce 6,400 motor drives. However, actual production was 5.200 units, and motor drives shipped amounted to 5,040 units. From the foregoing information, determine the manufacturing cost per unit.

a. $292.00
b. $275.00
c. $333.00
d. $342.00

Purchase this Solution

Solution Preview

1. Long lead times are the result of:

a. long setup times
b. large batch sizes
c. large inventories
d. all of the above
Answer (d) All the above

2. How are the objectives of Just-in-Time (JIT) manufacturing achieved?

a. Product-oriented production layout
b. Employee involvement
c. Supplier partnering
d. All of the above

Answer:d all the above

3. Which of the following drive work in process inventory levels higher?

a. Machine breakdowns
b. Production rate losses
c. Rework processing
d. All of the above

Answer: d (all the above)

4. Which of the following is characteristic of a just-in-time (JIT) system?

a. Fewer work in process account transactions
b. Work in process and raw materials accounts combine
c. Elimination of the direct labor account
d. All of the above

Answer (d) Fewer work in process account transactions

5. Which of the following is characteristic of a traditional cost system?

a. Many work in process account transactions
b. Reliance on financial performance measures
c. Many process control points ...

Purchase this Solution


Free BrainMass Quizzes
MS Word 2010-Tricky Features

These questions are based on features of the previous word versions that were easy to figure out, but now seem more hidden to me.

Social Media: Pinterest

This quiz introduces basic concepts of Pinterest social media

Organizational Behavior (OB)

The organizational behavior (OB) quiz will help you better understand organizational behavior through the lens of managers including workforce diversity.

Balance Sheet

The Fundamental Classified Balance Sheet. What to know to make it easy.

Production and cost theory

Understanding production and cost phenomena will permit firms to make wise decisions concerning output volume.