The progress report of a project contains the following data about the project costs:
BCWS = $ 46,500
BCWP = $ 49,200
ACWP = $ 54,250
BAC = $ 183,600

a.) Calculate CV

b.) Calculate CVP

c.) Calculate CPI

d.) Calculate SV

e.) Calculate SVP

f.) Calculate SPI

g.) Calculate EAC

h.) Calculate VAC

i.) Comment on the way the project is progressing.

Purchase this Solution

Solution Summary

The solution determines the sample calculation.

Solution provided by:
Education
  • BSc, Dokuz Eylul University
  • MBA, Texas A&M University-Kingsville
Recent Feedback
  • "Thanks"
  • "Thanks"
  • "This is a great help...Thank you"
  • "Thanks for the advice!"
  • "Oh my gosh u are awesome... A++"
Purchase this Solution


Free BrainMass Quizzes
Income Streams

In our ever changing world, developing secondary income streams is becoming more important. This quiz provides a brief overview of income sources.

Basic Social Media Concepts

The quiz will test your knowledge on basic social media concepts.

Change and Resistance within Organizations

This quiz intended to help students understand change and resistance in organizations

SWOT

This quiz will test your understanding of the SWOT analysis, including terms, concepts, uses, advantages, and process.

Learning Lean

This quiz will help you understand the basic concepts of Lean.