Project Cost Analysis: Sample Calculation
Not what you're looking for?
The progress report of a project contains the following data about the project costs:
BCWS = $ 46,500
BCWP = $ 49,200
ACWP = $ 54,250
BAC = $ 183,600
a.) Calculate CV
b.) Calculate CVP
c.) Calculate CPI
d.) Calculate SV
e.) Calculate SVP
f.) Calculate SPI
g.) Calculate EAC
h.) Calculate VAC
i.) Comment on the way the project is progressing.
Purchase this Solution
Solution Summary
The solution determines the sample calculation.
Education
- BSc, Dokuz Eylul University
- MBA, Texas A&M University-Kingsville
Recent Feedback
- "Thanks"
- "Thanks"
- "This is a great help...Thank you"
- "Thanks for the advice!"
- "Oh my gosh u are awesome... A++"
Purchase this Solution
Free BrainMass Quizzes
Income Streams
In our ever changing world, developing secondary income streams is becoming more important. This quiz provides a brief overview of income sources.
Basic Social Media Concepts
The quiz will test your knowledge on basic social media concepts.
Change and Resistance within Organizations
This quiz intended to help students understand change and resistance in organizations
SWOT
This quiz will test your understanding of the SWOT analysis, including terms, concepts, uses, advantages, and process.
Learning Lean
This quiz will help you understand the basic concepts of Lean.