Understanding Critical Path
Not what you're looking for?
What is the critical path?
ACTIVITY PREDECESSOR DURATION
A 2
B 5
C A,B 3
D B 6
E A,B 4
Purchase this Solution
Solution Summary
Ctitical Path explained with Example.
Solution Preview
Critical Path
Solution
Here is your problem solution, but below is some information that can help you understand what really critical path is.
ACTIVITY PREDECESSOR DURATION
A 2
B 5
C A,B 3
D B 6
E A,B 4
So Critical Path is 5 + 6 = 11 Days
Learn More About Critical Path
Before you start drawing critical path you really need to understand the definition of critical path. Let me first explain you what critical path means.
Critical Path: It is the longest duration path through the network diagram and determines the shortest time to complete the project. The easiest way to find the critical path is to add the ...
Purchase this Solution
Free BrainMass Quizzes
Accounting: Statement of Cash flows
This quiz tests your knowledge of the components of the statements of cash flows and the methods used to determine cash flows.
Motivation
This tests some key elements of major motivation theories.
Paradigms and Frameworks of Management Research
This quiz evaluates your understanding of the paradigm-based and epistimological frameworks of research. It is intended for advanced students.
Learning Lean
This quiz will help you understand the basic concepts of Lean.
Managing the Older Worker
This quiz will let you know some of the basics of dealing with older workers. This is increasingly important for managers and human resource workers as many countries are facing an increase in older people in the workforce