Please help with the following problem.

Activity Immediate Predecessor Time
A - 4
B - 3
C A 2
D B 7
E C,D 4
F B 5

13. Using the data in the table, what is the minimum possible time required for completing the project?
15. What is the latest possible time that C may be started without delaying the completion of the project?

Purchase this Solution

Solution Summary

This posting helps with problems regarding optimal work flow. The solution determines the maximum time and the time C must begin at. Step by step explanations are given.

Solution Preview

13. Using the data in the table, what is the minimum possible time required for completing the project?

Answer: B

From the table, we can design the optimal work flow as follows.
A and B are ...

Purchase this Solution


Free BrainMass Quizzes
Multiplying Complex Numbers

This is a short quiz to check your understanding of multiplication of complex numbers in rectangular form.

Know Your Linear Equations

Each question is a choice-summary multiple choice question that will present you with a linear equation and then make 4 statements about that equation. You must determine which of the 4 statements are true (if any) in regards to the equation.

Exponential Expressions

In this quiz, you will have a chance to practice basic terminology of exponential expressions and how to evaluate them.

Geometry - Real Life Application Problems

Understanding of how geometry applies to in real-world contexts

Graphs and Functions

This quiz helps you easily identify a function and test your understanding of ranges, domains , function inverses and transformations.